Friday 23 January 2015

MHRP East/West Bridge Link Works

Works to install the East/West Bridge link from the TRF into L3 of MHRP are about to kick into overdrive. Lend Lease have issued me with a program of details for the works to take place starting on the 28th January and concluding on the 23rd of March 2015.

As always we have envisaged a minimal interruption program, with works that involve drilling/coring to be done after hours/weekends and at times that do not impact on highly sensitive commercial operations.

The works will see the installation of two bridges:

1. An aerial bridge connecting the TRF on Level 4 to the MHRP building on Level 3 
2. Installation of a smaller bridge connecting the TRF and MHRP at ground level providing access to Kanooka Grove.

Below is a summary of key dates:

28th January 2015:

Egress from North Fire Escape (closest to TRF building) blocked for duration of works
Egress from Western Automatic Doors blocked for Installation of ground level bridge link 
Bike Racks removed (will be reinstated)

30/31st January 2015:

Lower Link Bridge Installed

31st January 2015- 24th Feb 2015:

Level 4 link bridge sections arrive and are assembled and installed

10-24th Feb 2015:

Generator relocation works begin, generator to be relocated and reinstated 24th Feb.

24th Feb 2015:

Threshold removed, facade cut and link bridge made secure

25th Feb 2015:

Lower link bridge cladding and stair installed

4- 23rd March 2015:

Lower Link bridge area reinstated, bike racks installed, L3 MHRP breakout space fitted out
  

For any further questions please do not hesitate to ask (steve.bouralexis@mimr-phi.org  or ph 95944325)